The remainder of the centre will include a common Mall with access to Specialty Shops.
The development will also comprise significant site works including re-diversion of Council STEDS drain. Lucid were involved in all pre-planning discussions with the Broken Hill Council in relation to the modifications to the Council STEDS drainage scheme and prepared the related documentation for Planning Approval purposes.
Lucid carried out all liaison with the associated Utilities (Country Energy and Country Water) early in the design program to ensure that their requirements were understood by the design team. All meetings held with the Utilities/Authorities were recorded and distributed to the relevant stake-holders. This early involvement ensured that the approval process was expedited.
Whilst the design of the building services installations for the major anchor tenants was generally in accordance with the applicable tenant design brief, Lucid were able to apply their innovative design skills to the centre in order to achieve strict local acoustic and sightline criterion for the development. |